MY WORK
(May 09 - Aug 09)

Shimizu has engaged a contract from the Road Transport Authorities (RTA) of Dubai to construct the Interchange No.8, a highway interchange bridge and surrounding roads of the Sheikh Zayed Road. The contract value is about US$150 million and original duration is from November 2007 to August 2009. I was out-stationed there for 3 months and involved in the claim analysis work. For this project, insufficient and erroneous consultant’s design made the construction difficult. In the end, the contractor had to resolve all the discrepancies through shop drawing submission and approval process.

General Work Procedures for a Project in Dubai:
- Preliminary study: by Engineer
- Preliminary design: by Engineer
- Final design and specification: by Engineer
- Tender, negotiation and contract award stage: Employer, Engineer, Contractor
- NOC request (get agreement from relevant authorities and agencies through Engineer): Contractor, Engineer
- Shop drawing preparation: by Contractor
- Method statement submission: by Contractor
- Construction by Contractor and inspection by Engineer (through RFI form: Request for Inspection, signed by Inspector, surveyor, material engineer, RE.)
- As built: by Contractor
- Final account and close out

Main Local Developers:
• Nakheel
• Emaar
• Etc.

Main Local Main Contractors:
• Al Habtoor Engineering
• Etc.



Bridge Plan


Access point


Pier column


Deck formwork using Peri system formwork


Casting diaphragm and bottom slab


Deck rebar


Post-tensioning stressing recess


Bearing pad