Concept

 

Define Resource under "Data"

Apply Resource to an activity

Resource Unit

Manhours or "Hrs" in short

 

Resource Production:

 

 

1) Rate:

 

Unit per day (Hrs/d)

2) Budgeted Quantity

 

Hrs

Resource Limit

Hrs / d

 

Resource Price:

 

 

1) Rate:

$ / Hrs

 

2) Budgeted Cost

 

$

Example

Take sample file "APEX" for instance.  Activity ID “AS310” and description “Site Preparation”.

 

Resource Name: FLD EN3

Limit: 8 Hrs / d

Price: $17 / Hrs

Unit per day: 4 Hrs / d

OD: 10d

Percent Complete: 80%

Scheduling

 

Resource

 

Cost

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Resource Profile

Resource Usage

 

Resource Limit

 

 

Earn Value

Resource and Cost Applied to an Activity

One activity can be applied more than one resource and more than one cost account.

Baseline

Baseline=Base Plan=Target Plan